US 11076509
Control systems and prediction methods for it cooling performance in containment
Granted 2021-07-27 · Filed 2018-01-24 · Application 15/879,163 · Utility · Kind B2 · Prior publication US 2018/0228060 A1, 2018-08-09
- Assignee as printed
- The Research Foundation for the State University, Binghamton, NY (US) · PatentsView label: The Research Foundation for The State University
- Inventors
- Husam Atallah ALISSA, Redmond, WA (US); Kourosh Nemati, Rockville, MD (US); Bahgat Sammakia, Binghamton, NY (US); Kanad Ghose, Vestal, NY (US)
- CPC, current
- H05K7/20836; G05B13/041; H05K7/20745
Abstract
A method of controlling a data center having a cold air cooling system, and at least one containment structure, comprising: determining a minimum performance constraint; determining optimum states of the cold air cooling system, a controlled leakage of air across the containment structure between a hot region and a cold air region, and information technology equipment for performing tasks to meet the minimum performance constraint, to minimize operating cost; and generating control signals to the cold air cooling system, a controlled leakage device, and the information technology equipment in accordance with the determined optimum states.
The claims as the USPTO long-text file prints them (text data version 20261117.3), split by PatentRef's claim parser (structure version 2): each claim's opening words, then one row for each element with its character offsets in the claim text, and the dependent claims under the claim they refer to. The split describes the text; it is not a reading of it. Each claim and each element has a link of its own. How the links are made.
Claim 1
Independent claim.
1. A method of controlling a data center having a cold air cooling system, and a cold air containment structure receiving air supplied by the cold air cooling system, for cooling of information technology equipment for performing tasks to meet a performance constraint, the information technology equipment having a cooling requirement and a bidirectional air flow path between the cold air containment structure having a first pressure and a hot air region having a second pressure, with an air flow direction and rate dependent on at least a pressure difference between the first pressure of the cold air containment structure and the second pressure of the hot air region, and a fan, such that a cooling of the information technology equipment is dependent on at least each of a state of the cold air cooling system and a state of the hot air region, comprising:
- Claim 1, element e1providing an air leakage device for controlling an air flow across a boundary of the cold air containment structure to the hot air region, distinct from the information technology equipment and the cold air cooling system, to thereby alter a pressure differential between the cold air containment structure at the first pressure and the hot air region at the second pressure; 866–1240
- Claim 1, element e2predicting a set of states comprising at least a state of the of the cold air cooling system, a state of the hot air region, and a state of the fan, that together result in reduced air flow rate for the information technology equipment with increasing fan speed, and is insufficient to meet the cooling requirement for the information technology equipment; 1242–1597
- Claim 1, element e3determining a state of the hot air region; 1599–1640
- Claim 1, element e4determining joint optimum states of: 1642–1677
- Claim 1, element e5the cold air cooling system, and the information technology equipment for performing tasks to meet the performance constraint; and 1679–1804
- Claim 1, element e6generating control signals for at least the cold air cooling system and the air leakage device, in accordance with the determined joint optimum states and the state of the hot air region, to induce controlled air flows for the information technology equipment over a range comprising air flow from the cold air containment structure to the hot air region, and from the hot air region to the cold air containment structure, while actively avoiding operation at the predicted set of states that together result in an air flow rate for the information technology equipment that is insufficient to meet the cooling requirement for the information technology equipment, to selectively control a flow of air in the bidirectional air flow path of the information technology equipment to meet the cooling requirement while the information technology equipment meets the performance constraint.1810–2694
17 dependent claims: 2 to 18 (2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18 on claim 1)
Claim 2
Depends on claim 1.
2. The method according to claim 1 , further comprising
- Claim 2, element e1receiving air pressure data from the at least one cold air containment structure, air pressure data from the hot air region, thermal data, and fan speed data from the information technology equipment, and determining the joint optimum states selectively in dependence on the air pressure data from the at least one cold air containment structure, air pressure data from the hot air region, the thermal data, and the fan speed data.56–486
Claim 3
Depends on claim 1.
3. The method according to claim 1 , wherein
- Claim 3, element e1the information technology equipment has an intrinsic thermal excursion throttling response that reduces processing performance under predetermined thermal conditions, further comprising modelling the throttling response of the information technology equipment to the generated control signals and generating the control signals further in accordance with the modelled throttling response to meet the performance constraint.45–468
Claim 4
Depends on claim 1.
4. The method according to claim 1 , wherein
- Claim 4, element e1the determined joint optimum states further provide a margin of statistical safety based on prior operating statistics of the data center.45–182
Claim 5
Depends on claim 1.
5. The method according to claim 1 , wherein
- Claim 5, element e1the information technology equipment under control of the control signals is distributed across a plurality of racks having different respective rack locations within the data center, further comprising optimizing an allocation of task performance to the information technology equipment at a respective rack location within the data center.45–385
Claim 6
Depends on claim 1.
6. The method according to claim 1 , wherein
- Claim 6, element e1the determined joint optimum states are dependent on a computational model of the data center.45–138
Claim 7
Depends on claim 1.
7. The method according to claim 1 , wherein
- Claim 7, element e1the determined joint optimum states are dependent on at least a computational flow dynamics model of the cold air cooling system, the information technology equipment, and the at least one cold air containment structure.45–264
Claim 8
Depends on claim 1.
8. The method according to claim 1 , wherein
- Claim 8, element e1the determined joint optimum states include, within a permissible range of operation defined by the control signals, a predicted reverse of flow direction of air through the information technology equipment from the hot air region comprising a hot aisle to the cold air containment structure comprising a cold aisle.45–360
Claim 9
Depends on claim 1.
9. The method according to claim 1 , wherein
- Claim 9, element e1the generated control signals are dependent on an adaptively updated computational model of the data center.45–152
Claim 10
Depends on claim 1.
10. The method according to claim 1 , wherein
- Claim 10, element e1the determined joint optimum states are dependent on a hybrid of an automatically defined computational model of the data center and a physics model of the data center.46–213
Claim 11
Depends on claim 1.
11. The method according to claim 1 , wherein
- Claim 11, element e1the data center comprises a plurality of pieces of information technology equipment, further comprising predicting an air flow through each piece of information technology equipment of the data center, 46–246
- Claim 11, element e2wherein the determined joint optimum states are dependent on the predicted air flow through each piece of information technology equipment of the data center.248–405
Claim 12
Depends on claim 1.
12. The method according to claim 1 , wherein
- Claim 12, element e1said predicting the set of states further comprises predicting a null air flow state for the information technology equipment due to back pressure of hot air region against operation of the fan.46–239
Claim 13
Depends on claim 1.
13. The method according to claim 1 , further comprising
- Claim 13, element e1controlling the at least one cold air containment structure to selectively vent, and thereby reduce the first pressure, in response to the generated control signals.57–221
Claim 14
Depends on claim 1.
14. The method according to claim 1 , further comprising
- Claim 14, element e1controlling a damper associated with the at least cold air one containment structure to selectively restrict an air flow in response to the generated control signals.57–222
Claim 15
Depends on claim 1.
15. The method according to claim 1 , wherein
- Claim 15, element e1the determining the joint optimum states is responsive to time lags within each of the cold air cooling system, a controlled leakage device, and the information technology equipment.46–227
Claim 16
Depends on claim 1.
16. The method according to claim 1 , further comprising
- Claim 16, element e1predicting a prospective thermal event dependent on the control signals, and issuing a warning due to the prospective thermal event.57–188
Claim 17
Depends on claim 1.
17. The method according to claim 1 , wherein
- Claim 17, element e1the performance constraint is a minimum performance constraint, further comprising issuing a warning of a failure to meet the minimum performance constraint.46–202
Claim 18
Depends on claim 1.
18. The method according to claim 1 , further comprising
- Claim 18, element e1detecting an airflow reduction in the cold air cooling system, and selectively in response thereto, imposing a power cap on a first portion of the information technology equipment to selectively mitigate a reduction in cold air available to a second portion of the information technology equipment.57–354
Claim 19
Independent claim.
19. A system for controlling a data center having a cold air cooling system, and at least one cold air containment structure, comprising:
- Claim 19, element e1a sensor input, configured to receive sensor data representing thermal and pneumatic information from within the data center; 138–262
- Claim 19, element e2at least one automated processor, configured to: 264–311
- Claim 19, element e3determine a temperature-dependent performance constraint; 313–369
- Claim 19, element e4determine, according to joint optimization criteria, joint optimum states of: 371–447
- Claim 19, element e5the cold air cooling system, a controlled leakage device for controlling air flow across a boundary of the cold air containment structure, distinct from the information technology equipment and the cold air cooling system, the air flow being dependent on a first pressure provided dependent on a state of the cold air containment structure, and a second pressure of a hot air region, and information technology equipment for performing tasks to meet the performance constraint, having a bidirectional air flow path between the cold air containment structure and the hot air region, and a flow direction and rate dependent on at least a differential pressure between the cold air containment structure and the hot air region and a fan speed, 449–1188
- Claim 19, element e6wherein at least one state exists where the fan nulls a non-zero back pressure of the hot air region with respect to the cold air containment structure, to provide insufficient cooling of the information technology equipment; and 1190–1414
- Claim 19, element e7define control signals for the cold air cooling system and the controlled leakage device, in accordance with the determined joint optimum states and a state of the hot air region; and 1420–1598
- Claim 19, element e8a control output, configured to provide control signals for the cold air cooling system and the controlled leakage device, to induce air flows through the information technology equipment comprising air flow from the cold air containment structure to the hot air region, and from the hot air region to the cold air containment structure, to selectively avoid the at least on state where the fan nulls a non-zero back pressure of the hot air region with respect to the cold air containment structure, to provide insufficient cooling of the information technology equipment.1604–2175
Claim 20
Independent claim.
20. A data center controller, comprising:
- Claim 20, element e1a sensor input configured to receive at least thermal data from within a data center; 42–126
- Claim 20, element e2at least one automated processor, configured to: 128–175
- Claim 20, element e3determine a set of jointly optimized states of: 177–223
- Claim 20, element e4a cold air cooling system for the data center, a controlled leakage device for controlling air flow across a boundary of a cold air containment structure, distinct from the information technology equipment and the cold air cooling system, receiving cold air from the cold air cooling system, within the data center, and information technology equipment within the data center for performing tasks within a performance constraint, having a bidirectional cooling path between the cold air cooling system and a hot air region, having a flow rate and direction dependent on a fan speed of a cooling fan and a differential pressure of between the cold air cooling system and a hot air region, and having a cooling need dependent on tasks performed by the information technology equipment wherein a state exists within the data center where an increase in fan speed acts to reduce an air flow through the information technology equipment, and thereby reduce cooling, 225–1184
- Claim 20, element e5wherein the set of jointly optimized states comprise an air flow from the cold air containment structure through the information technology equipment to the hot air region, and air flow from the hot air region through the information technology equipment to the cold air containment structure; and 1186–1478
- Claim 20, element e6define control signals for at least the controlled leakage device, in accordance with the determined joint optimum states the differential pressure, and a predicted effect of fan speed on air flow comprising a predicted state wherein the increase in fan speed acts to reduce an air flow through the information technology equipment against the differential pressure, to ensure performance of the tasks within the performance constraint by avoiding operation in the predicted state with insufficient air flow; and 1484–1991
- Claim 20, element e7a control output, configured to provide control signals for the controlled leakage device, dependent on the defined control signals.1997–2128
1. A method of controlling a data center having a cold air cooling system, and a cold air containment structure receiving air supplied by the cold air cooling system, for cooling of information technology equipment for performing tasks to meet a performance constraint, the information technology equipment having a cooling requirement and a bidirectional air flow path between the cold air containment structure having a first pressure and a hot air region having a second pressure, with an air flow direction and rate dependent on at least a pressure difference between the first pressure of the cold air containment structure and the second pressure of the hot air region, and a fan, such that a cooling of the information technology equipment is dependent on at least each of a state of the cold air cooling system and a state of the hot air region, comprising: providing an air leakage device for controlling an air flow across a boundary of the cold air containment structure to the hot air region, distinct from the information technology equipment and the cold air cooling system, to thereby alter a pressure differential between the cold air containment structure at the first pressure and the hot air region at the second pressure; predicting a set of states comprising at least a state of the of the cold air cooling system, a state of the hot air region, and a state of the fan, that together result in reduced air flow rate for the information technology equipment with increasing fan speed, and is insufficient to meet the cooling requirement for the information technology equipment; determining a state of the hot air region; determining joint optimum states of: the cold air cooling system, and the information technology equipment for performing tasks to meet the performance constraint; and generating control signals for at least the cold air cooling system and the air leakage device, in accordance with the determined joint optimum states and the state of the hot air region, to induce controlled air flows for the information technology equipment over a range comprising air flow from the cold air containment structure to the hot air region, and from the hot air region to the cold air containment structure, while actively avoiding operation at the predicted set of states that together result in an air flow rate for the information technology equipment that is insufficient to meet the cooling requirement for the information technology equipment, to selectively control a flow of air in the bidirectional air flow path of the information technology equipment to meet the cooling requirement while the information technology equipment meets the performance constraint.
2. The method according to claim 1 , further comprising receiving air pressure data from the at least one cold air containment structure, air pressure data from the hot air region, thermal data, and fan speed data from the information technology equipment, and determining the joint optimum states selectively in dependence on the air pressure data from the at least one cold air containment structure, air pressure data from the hot air region, the thermal data, and the fan speed data.
3. The method according to claim 1 , wherein the information technology equipment has an intrinsic thermal excursion throttling response that reduces processing performance under predetermined thermal conditions, further comprising modelling the throttling response of the information technology equipment to the generated control signals and generating the control signals further in accordance with the modelled throttling response to meet the performance constraint.
4. The method according to claim 1 , wherein the determined joint optimum states further provide a margin of statistical safety based on prior operating statistics of the data center.
5. The method according to claim 1 , wherein the information technology equipment under control of the control signals is distributed across a plurality of racks having different respective rack locations within the data center, further comprising optimizing an allocation of task performance to the information technology equipment at a respective rack location within the data center.
6. The method according to claim 1 , wherein the determined joint optimum states are dependent on a computational model of the data center.
7. The method according to claim 1 , wherein the determined joint optimum states are dependent on at least a computational flow dynamics model of the cold air cooling system, the information technology equipment, and the at least one cold air containment structure.
8. The method according to claim 1 , wherein the determined joint optimum states include, within a permissible range of operation defined by the control signals, a predicted reverse of flow direction of air through the information technology equipment from the hot air region comprising a hot aisle to the cold air containment structure comprising a cold aisle.
9. The method according to claim 1 , wherein the generated control signals are dependent on an adaptively updated computational model of the data center.
10. The method according to claim 1 , wherein the determined joint optimum states are dependent on a hybrid of an automatically defined computational model of the data center and a physics model of the data center.
11. The method according to claim 1 , wherein the data center comprises a plurality of pieces of information technology equipment, further comprising predicting an air flow through each piece of information technology equipment of the data center, wherein the determined joint optimum states are dependent on the predicted air flow through each piece of information technology equipment of the data center.
12. The method according to claim 1 , wherein said predicting the set of states further comprises predicting a null air flow state for the information technology equipment due to back pressure of hot air region against operation of the fan.
13. The method according to claim 1 , further comprising controlling the at least one cold air containment structure to selectively vent, and thereby reduce the first pressure, in response to the generated control signals.
14. The method according to claim 1 , further comprising controlling a damper associated with the at least cold air one containment structure to selectively restrict an air flow in response to the generated control signals.
15. The method according to claim 1 , wherein the determining the joint optimum states is responsive to time lags within each of the cold air cooling system, a controlled leakage device, and the information technology equipment.
16. The method according to claim 1 , further comprising predicting a prospective thermal event dependent on the control signals, and issuing a warning due to the prospective thermal event.
17. The method according to claim 1 , wherein the performance constraint is a minimum performance constraint, further comprising issuing a warning of a failure to meet the minimum performance constraint.
18. The method according to claim 1 , further comprising detecting an airflow reduction in the cold air cooling system, and selectively in response thereto, imposing a power cap on a first portion of the information technology equipment to selectively mitigate a reduction in cold air available to a second portion of the information technology equipment.
19. A system for controlling a data center having a cold air cooling system, and at least one cold air containment structure, comprising: a sensor input, configured to receive sensor data representing thermal and pneumatic information from within the data center; at least one automated processor, configured to: determine a temperature-dependent performance constraint; determine, according to joint optimization criteria, joint optimum states of: the cold air cooling system, a controlled leakage device for controlling air flow across a boundary of the cold air containment structure, distinct from the information technology equipment and the cold air cooling system, the air flow being dependent on a first pressure provided dependent on a state of the cold air containment structure, and a second pressure of a hot air region, and information technology equipment for performing tasks to meet the performance constraint, having a bidirectional air flow path between the cold air containment structure and the hot air region, and a flow direction and rate dependent on at least a differential pressure between the cold air containment structure and the hot air region and a fan speed, wherein at least one state exists where the fan nulls a non-zero back pressure of the hot air region with respect to the cold air containment structure, to provide insufficient cooling of the information technology equipment; and define control signals for the cold air cooling system and the controlled leakage device, in accordance with the determined joint optimum states and a state of the hot air region; and a control output, configured to provide control signals for the cold air cooling system and the controlled leakage device, to induce air flows through the information technology equipment comprising air flow from the cold air containment structure to the hot air region, and from the hot air region to the cold air containment structure, to selectively avoid the at least on state where the fan nulls a non-zero back pressure of the hot air region with respect to the cold air containment structure, to provide insufficient cooling of the information technology equipment.
20. A data center controller, comprising: a sensor input configured to receive at least thermal data from within a data center; at least one automated processor, configured to: determine a set of jointly optimized states of: a cold air cooling system for the data center, a controlled leakage device for controlling air flow across a boundary of a cold air containment structure, distinct from the information technology equipment and the cold air cooling system, receiving cold air from the cold air cooling system, within the data center, and information technology equipment within the data center for performing tasks within a performance constraint, having a bidirectional cooling path between the cold air cooling system and a hot air region, having a flow rate and direction dependent on a fan speed of a cooling fan and a differential pressure of between the cold air cooling system and a hot air region, and having a cooling need dependent on tasks performed by the information technology equipment wherein a state exists within the data center where an increase in fan speed acts to reduce an air flow through the information technology equipment, and thereby reduce cooling, wherein the set of jointly optimized states comprise an air flow from the cold air containment structure through the information technology equipment to the hot air region, and air flow from the hot air region through the information technology equipment to the cold air containment structure; and define control signals for at least the controlled leakage device, in accordance with the determined joint optimum states the differential pressure, and a predicted effect of fan speed on air flow comprising a predicted state wherein the increase in fan speed acts to reduce an air flow through the information technology equipment against the differential pressure, to ensure performance of the tasks within the performance constraint by avoiding operation in the predicted state with insufficient air flow; and a control output, configured to provide control signals for the controlled leakage device, dependent on the defined control signals.
The text of each claim as printed, for pasting a claim word for word. The links in the tree view name the same claims and elements.
Status
active
As of 2026-11-17, the USPTO record for US 11076509 shows no unresolved maintenance-fee lapse, and the term end computed from the dates in that record is 2039-03-21 (20 years from filing, plus 421 days of patent term adjustment), a date not yet passed (data version 20261117.2).
- Basis
- term_20y · pta_days:421 (20 years from filing, plus 421 days of patent term adjustment)
- Term end
- 2039-03-21 Computed from the dates in the USPTO record
- Fee lapse
- none on record
- Reinstatement
- none on record; reinstatement_possible: false, not lapsed
- As of
- 2026-11-17
- Data version
- 20261117.2
A fact about the record with its basis and its as-of date, not legal advice.
Citations
References cited on the grant: 716 US patent documents · Cited by: 180 US patents in this data · Lists through the API: /api/v1/patent/us_patent_citation/11076509/ (needs a free key, as the links under Get this as data)
Family outside the US
Google Patents Public Datasets lists no publication outside the US in this patent's family (read 2026-10-15).
This patent's family on USPTO Global Dossier
Family data from Google Patents Public Datasets, used under CC BY 4.0.
Record JSON
{
"patent_id": "11076509",
"status": "active",
"basis": [
"term_20y",
"pta_days:421"
],
"reinstatement_possible": false,
"reinstatement_basis": "not lapsed",
"expiry_date_estimated": "2039-03-21",
"lapse_date": null,
"reinstated_date": null,
"as_of": "2026-11-17",
"data_version": "20261117.2",
"catalog_data_version": "20261117.2",
"permalink": "https://patentref.io/p/11076509?v=20261117.2",
"next_steps": [
{
"kind": "record",
"url": "https://patentref.io/p/11076509?v=20261117.2",
"audience": "human"
},
{
"kind": "patent",
"url": "https://patentref.io/api/v1/patent/11076509/",
"audience": "agent"
},
{
"kind": "fee_events",
"tool": "uspto_patent_center",
"url": "https://patentcenter.uspto.gov/applications?patentNumber=11076509",
"audience": "agent"
}
]
}
Get this as data
- Full record
/api/v1/patent/11076509/ - Status record
/api/v1/lapse/status/11076509/ - Claim tree
/api/v1/structure/claims/11076509/ - Brief
/api/v1/structure/brief/11076509/
These four links need a free key (1,000 requests a month). Opened in a browser, which sends no key, they answer 403. Get a free key on the sign-up page, then send it in the X-Api-Key header. To see the shape of an answer without a key, open Try it.