Adaptive hydraulic fracturing controller for controlled breakdown technology

Granted 2021-08-10 · Filed 2017-12-29 · Application 16/346,154 · Utility · Kind B2 · Prior publication US 2020/0056466 A1, 2020-02-20

Assignee as printed
  • Halliburton Energy Services, Inc., Houston, TX (US)
Inventors
Mehdi Mazrooee, Double Oak, TX (US); Michael Linley Fripp, Carrollton, TX (US); Matthew Lewis Lahman, Houston, TX (US); Mark Adams, Duncan, OK (US)
CPC, current
E21B43/26; E21B41/00; E21B43/2607; E21B43/267; E21B47/06; F04B15/00; F04B49/00; F04B2207/02

Abstract

A method for hydraulically fracturing a subterranean formation includes sending a first command from a controller to a pump to achieve a first target flow rate for a fracturing fluid being injected into a subterranean formation during a fracturing operation. Monitoring an injection property of the fracturing operation. Determining a rate of change of the pressure over a first time period. Determining, by the controller, a second target flow rate based, at least in part, on the rate of change of the pressure. Sending a second command from the controller to the pump to achieve the second target flow rate for the fracturing fluid.

Claims

20 claims · independent 1, 9 and 16

The claims as the USPTO long-text file prints them (text data version 20261117.3), split by PatentRef's claim parser (structure version 2): each claim's opening words, then one row for each element with its character offsets in the claim text, and the dependent claims under the claim they refer to. The split describes the text; it is not a reading of it. Each claim and each element has a link of its own. How the links are made.

Claim 1

Independent claim.

1. A method comprising:

  1. Claim 1, element e1sending a first command from a controller to a pump to achieve a first target flow rate for a fracturing fluid being injected into a subterranean formation during a fracturing operation; 24–209
  2. Claim 1, element e2monitoring an injection property of the fracturing operation; 211–271
  3. Claim 1, element e3determining a rate of change of the injection property over a first time period; 273–352
  4. Claim 1, element e4determining, by the controller, a second target flow rate based, at least in part, on the rate of change of the injection property, 354–484
  5. Claim 1, element e5wherein determining the second target flow rate comprises, based on determining that the rate of change over the first time period indicates an increase or a decrease exceeding a threshold, reducing or increasing a value of a flow rate step; and 486–726
  6. Claim 1, element e6determining the second target flow rate to be the first target flow rate plus the flow rate step; and 732–828
  7. Claim 1, element e7sending a second command from the controller to the pump to achieve the second target flow rate for the fracturing fluid.834–954
7 dependent claims: 2 to 8 (2, 3, 4, 5 on claim 1; 6, 7 on 5; 8 on 7)

Claim 2

Depends on claim 1.

2. The method of claim 1 , wherein

  1. Claim 2, element e1the injection property comprises at least one of a pressure of the fracturing fluid, a pressure amplitude in response to achieving the first target flow rate, hydraulic power of the pump, and rotations per minute of the pump.35–259

Claim 3

Depends on claim 1.

3. The method of claim 1 , wherein

  1. Claim 3, element e1determining the second target flow rate based, at least in part, on the rate of change of the injection property comprises: 35–157
  2. Claim 3, element e2based on determining that the rate of change over the first time period indicates an increase exceeding a first threshold, reducing a value of a flow rate step; 159–318
  3. Claim 3, element e3based on determining that the rate of change over the first time period indicates a decrease exceeding a second threshold, increasing the value of the flow rate step; and 320–485
  4. Claim 3, element e4determining the second target flow rate to be the first target flow rate plus the flow rate step.491–587

Claim 4

Depends on claim 1.

4. The method of claim 1 , wherein

  1. Claim 4, element e1determining the second target flow rate based, at least in part, on the rate of change of the injection property comprises: 35–157
  2. Claim 4, element e2based on determining that the rate of change falls within a first range of a set of ranges, identifying a flow rate step associated with the first range; and 159–311
  3. Claim 4, element e3determining the second target flow rate to be the first target flow rate plus the flow rate step associated with the first range.317–445

Claim 5

Depends on claim 1.

5. The method of claim 1 further comprising:

  1. Claim 5, element e1based on the injection property of the fracturing operation, determining, by the controller, to increase a flow rate of the fracturing fluid; 45–185
  2. Claim 5, element e2wherein sending the second command from the controller to the pump is in response to determining to increase the flow rate.187–309

Claim 6

Depends on claim 5.

6. The method of claim 5 , wherein

  1. Claim 6, element e1determining to increase the flow rate of the fracturing fluid comprises determining that the rate of change of the first time period indicates that the injection flow property is decreasing.35–224

Claim 7

Depends on claim 5.

7. The method of claim 5 , wherein

  1. Claim 7, element e1determining to increase the flow rate of the fracturing fluid comprises determining that a maximum time for the first target flow rate has expired.35–181

Claim 8

Depends on claim 7.

8. The method of claim 7 , further comprising:

  1. Claim 8, element e1comparing the rate of change for the first time period to a rate of change for a previous time period; 47–148
  2. Claim 8, element e2based on determining that the rate of change for the first time period is greater than the rate of change for the previous time period, increasing the maximum time; and 150–313
  3. Claim 8, element e3based on determining that the rate of change for the first time period is less than the rate of change for the previous time period, decreasing the maximum time.319–479

Claim 9

Independent claim.

9. A fracturing control system comprising:

  1. Claim 9, element e1a fluid system that mixes and dispenses a fracturing fluid; 43–101
  2. Claim 9, element e2a pump which receives and conveys the fracturing fluid into a wellbore to hydraulically fracture a subterranean formation; and 103–224
  3. Claim 9, element e3a controller communicably coupled to and configured to operate the pump, 230–301
  4. Claim 9, element e4wherein the controller comprises a processor and a machine-readable medium having program code executable by the processor to cause the controller to: 303–452
  5. Claim 9, element e5send a first command to the pump to achieve a first target flow rate for a fracturing fluid being injected into a subterranean formation; 454–590
  6. Claim 9, element e6monitor a pressure of the fracturing fluid being injected into the subterranean formation; 592–681
  7. Claim 9, element e7determine a rate of change of the pressure over a first time period; 683–750
  8. Claim 9, element e8determine a second target flow rate based, at least in part, on the rate of change of the pressure, 752–850
  9. Claim 9, element e9wherein determining the second target flow rate comprises, based on determining that the rate of change over the first time period indicates an increase or a decrease exceeding a threshold, reducing or increasing a value of a flow rate step; and 852–1092
  10. Claim 9, element e10determining the second target flow rate to be the first target flow rate plus the flow rate step; and 1098–1194
  11. Claim 9, element e11send a second command to the pump to achieve the second target flow rate for the fracturing fluid.1200–1297
6 dependent claims: 10 to 15 (10, 11, 14 on claim 9; 12 on 11; 13 on 12; 15 on 14)

Claim 10

Depends on claim 9.

10. The fracturing control system of claim 9 , wherein

  1. Claim 10, element e1the program code executable by the processor to cause the controller to determine the second target flow rate based, at least in part, on the rate of change of the pressure comprises program code executable by the processor to cause the controller to: 55–305
  2. Claim 10, element e2based on a determination that the rate of change over the first time period indicates an increase exceeding a first threshold, reduce a value of a flow rate step; 307–468
  3. Claim 10, element e3based on a determination that the rate of change over the first time period indicates a decrease exceeding a second threshold, increase the value of the flow rate step; and 470–637
  4. Claim 10, element e4determine the second target flow rate to be the first target flow rate plus the flow rate step.643–737

Claim 11

Depends on claim 9.

11. The fracturing control system of claim 9 , wherein

  1. Claim 11, element e1the program code executable by the processor to cause the controller to determine the second target flow rate based, at least in part, on the rate of change of the pressure comprises program code executable by the processor to cause the controller to: 55–305
  2. Claim 11, element e2based on a determination that the rate of change falls within a first range of a set of ranges, identify a flow rate step associated with the first range; and 307–460
  3. Claim 11, element e3determine the second target flow rate to be the first target flow rate plus the flow rate step associated with the first range.466–592

Claim 12

Depends on claim 11.

12. The fracturing control system of claim 11 , wherein

  1. Claim 12, element e1the program code executable by the processor to cause the controller to determine to increase the flow rate of the fracturing fluid comprises program code executable by the processor to cause the controller to determine that a maximum time for the first target flow rate has expired.56–338

Claim 13

Depends on claim 12.

13. The fracturing control system of claim 12 , wherein

  1. Claim 13, element e1the program code further comprises program code executable by the processor to cause the controller to: 56–158
  2. Claim 13, element e2compare the rate of change for the first time period to a rate of change for a previous time period; 160–259
  3. Claim 13, element e3based on a determination that the rate of change for the first time period is greater than the rate of change for the previous time period, increase the maximum time; and 261–426
  4. Claim 13, element e4based on a determination that the rate of change for the first time period is less than the rate of change for the previous time period, decrease the maximum time.432–594

Claim 14

Depends on claim 9.

14. The fracturing control system of claim 9 , wherein

  1. Claim 14, element e1the program code further comprises program code executable by the processor to cause the controller to: 55–157
  2. Claim 14, element e2based on the pressure of the fracturing fluid being injected into the subterranean formation, determine, by the controller, to increase a flow rate of the fracturing fluid; 159–330
  3. Claim 14, element e3wherein the program code executable by the processor to cause the controller to send the second command from the controller to the pump is executed in response to determining to increase the flow rate.332–532

Claim 15

Depends on claim 14.

15. The fracturing control system of claim 14 , wherein

  1. Claim 15, element e1the program code executable by the processor to cause the controller to determine to increase the flow rate of the fracturing fluid comprises program code executable by the processor to cause the controller to determine that the rate of change of the first time period indicates that the pressure is decreasing.56–366

Claim 16

Independent claim.

16. One or more non-transitory machine-readable media having program code stored therein, the program code to: send a first command to a pump to achieve a first target flow rate for a fracturing fluid being injected into a subterranean formation; monitor a pressure of the fracturing fluid being injected into the subterranean formation; determine a rate of change of the pressure over a first time period; determine a second target flow rate based, at least in part, on the rate of change of the pressure, wherein

  1. Claim 16, element e1determining the second target flow rate comprises, based on determining that the rate of change over the first time period indicates an increase or a decrease exceeding a threshold, reducing or increasing a value of a flow rate step; and 515–747
  2. Claim 16, element e2determining the second target flow rate to be the first target flow rate plus the flow rate step; and 753–849
  3. Claim 16, element e3send a second command to the pump to achieve the second target flow rate for the fracturing fluid.855–952
4 dependent claims: 17 to 20 (17, 18 on claim 16; 19 on 18; 20 on 19)

Claim 17

Depends on claim 16.

17. The machine-readable media of claim 16 , wherein

  1. Claim 17, element e1the program code to determine the second target flow rate based, at least in part, on the rate of change of the pressure comprises program code to: 53–199
  2. Claim 17, element e2based on a determination that the rate of change over the first time period indicates an increase exceeding a first threshold, reduce a value of a flow rate step; 201–362
  3. Claim 17, element e3based on a determination that the rate of change over the first time period indicates a decrease exceeding a second threshold, increase the value of the flow rate step; and 364–531
  4. Claim 17, element e4determine the second target flow rate to be the first target flow rate plus the flow rate step.537–631

Claim 18

Depends on claim 16.

18. The machine-readable media of claim 16 , wherein

  1. Claim 18, element e1the program code to determine the second target flow rate based, at least in part, on the rate of change of the pressure comprises program code to: 53–199
  2. Claim 18, element e2based on a determination that the rate of change falls within a first range of a set of ranges, identify a flow rate step associated with the first range; and 201–354
  3. Claim 18, element e3determine the second target flow rate to be the first target flow rate plus the flow rate step associated with the first range.360–486

Claim 19

Depends on claim 18.

19. The machine-readable media of claim 18 , wherein

  1. Claim 19, element e1the program code to determine to increase the flow rate of the fracturing fluid comprises program code to determine that a maximum time for the first target flow rate has expired.53–231

Claim 20

Depends on claim 19.

20. The machine-readable media of claim 19 , wherein

  1. Claim 20, element e1the program code further comprises program code to: 53–103
  2. Claim 20, element e2compare the rate of change for the first time period to a rate of change for a previous time period; 105–204
  3. Claim 20, element e3based on a determination that the rate of change for the first time period is greater than the rate of change for the previous time period, increase the maximum time; and 206–371
  4. Claim 20, element e4based on a determination that the rate of change for the first time period is less than the rate of change for the previous time period, decrease the maximum time.377–539

Status

active

As of 2026-11-17, the USPTO record for US 11085282 shows no unresolved maintenance-fee lapse, and the term end computed from the dates in that record is 2037-06-12 (20 years from the filing of a parent application on 2016-12-30, plus 164 days of patent term adjustment), a date not yet passed (data version 20261117.2).

Basis
term_20y · pta_days:164 (20 years from the filing of a parent application on 2016-12-30, plus 164 days of patent term adjustment)
Term end
2037-06-12 Computed from the dates in the USPTO record
Fee lapse
none on record
Reinstatement
none on record; reinstatement_possible: false, not lapsed
As of
2026-11-17
Data version
20261117.2

A fact about the record with its basis and its as-of date, not legal advice.

Citations

References cited on the grant: 3 US patent documents · Cited by: 89 US patents in this data · Lists through the API: /api/v1/patent/us_patent_citation/11085282/ (needs a free key, as the links under Get this as data)

Family outside the US

Publications outside the US that Google Patents Public Datasets lists in the same patent family as US 11085282 (read 2026-10-15). Their legal status is not shown here.

OfficeNumberKindPublished
AU2017388570A12019-04-04
AU2016434454A12019-04-11
AU2017388570B22022-12-01
AU2016434454B22023-01-19
CA3040317A12018-07-05
CA3041239A12018-07-05
CA3040317C2021-03-30
CA3041239C2021-08-31
NO20190347A12019-03-15
NO20190348A12019-03-15
NO349853B12026-05-26
SA519401876B12023-02-15
WO2018125176A12018-07-05
WO2018126106A12018-07-05

This patent's family on USPTO Global Dossier

Family data from Google Patents Public Datasets, used under CC BY 4.0.

Record JSON
{
 "patent_id": "11085282",
 "status": "active",
 "basis": [
  "term_20y",
  "pta_days:164"
 ],
 "reinstatement_possible": false,
 "reinstatement_basis": "not lapsed",
 "expiry_date_estimated": "2037-06-12",
 "lapse_date": null,
 "reinstated_date": null,
 "as_of": "2026-11-17",
 "data_version": "20261117.2",
 "catalog_data_version": "20261117.2",
 "permalink": "https://patentref.io/p/11085282?v=20261117.2",
 "next_steps": [
  {
   "kind": "record",
   "url": "https://patentref.io/p/11085282?v=20261117.2",
   "audience": "human"
  },
  {
   "kind": "patent",
   "url": "https://patentref.io/api/v1/patent/11085282/",
   "audience": "agent"
  },
  {
   "kind": "fee_events",
   "tool": "uspto_patent_center",
   "url": "https://patentcenter.uspto.gov/applications?patentNumber=11085282",
   "audience": "agent"
  }
 ]
}

Get this as data

These four links need a free key (1,000 requests a month). Opened in a browser, which sends no key, they answer 403. Get a free key on the sign-up page, then send it in the X-Api-Key header. To see the shape of an answer without a key, open Try it.

Elsewhere

Cite this record

https://patentref.io/p/11085282?v=20261117.2

Data 20261117.2 · as of 2026-11-17